How long does a bathroom remodel take?
Estimated duration is four weeks!
Demolition & Site Prep
1–2 Days. Quick but messy.
Rough-in (Plumbing/Electrical)
3–5 Days. Moving pipes or wires for the new layout.
Inspection (Rough-in)
1–5 Days. Scheduling the city inspector is out of the contractor's control and can cause a brief pause.
Drywall, Insulation, Cement Board
3–4 Days. Getting the walls ready for finishes.
Waterproofing & Tile
5–10 Days. Tiling is detail-oriented and includes cure time for thinset/grout. This cannot be rushed.
Installations & Finishes
4–7 Days. Installing the vanity, toilet, lights, trim, paint, and shower glass.
Final Inspection & Punch List
1–5 Days. The final review and fix-up of small details.